Published: 18:39, January 16, 2024 | Updated: 20:55, January 16, 2024
Japan to start fourth release of Fukushima water in late Feb
By Agencies

This photo taken on March 6, 2023 shows the Fukushima Daiichi nuclear power plant in Futabacho, Futabagun of Fukushima prefecture, Japan. (PHOTO / XINHUA)

TOKYO - Tokyo Electric Power Company plans to start a fourth release of water from the wrecked Fukushima Daiichi Nuclear Power Plant in late February, an official said on Tuesday.

The staged water releases began last August in what Japan says is a key step in decommissioning the plant hit by an earthquake and tsunami in 2011 in the world's worst nuclear disaster since Chernobyl.

In the fourth release, about 7,800 cubic meters (275,454 cubic feet) of the water will be sent into the Pacific Ocean, similar to the previous three discharges

READ MORE: Pacific islands urge Japan to delay release of Fukushima waste

In the fourth release, about 7,800 cubic meters (275,454 cubic feet) of the water will be sent into the Pacific Ocean, similar to the previous three discharges, Junichi Matsumoto, the Tepco official overseeing the operation, said in a media presentation.

As part of the decades-long plan to release the water, the fifth and sixth discharges will occur during the fiscal year ending in March 2025, his presentation showed.

After initially stopping all nuclear reactors after the 2011 Fukushima disaster, Japan has started to gradually bring nuclear power back to its energy mix as it tries to cut its carbon footprint and reduce imports of fossil fuels.

But the powerful earthquake that struck Japan's Ishikawa prefecture on New Year's Day caused water spillover from spent nuclear fuel pools and oil leaks at the idled Shika nuclear power station in the region, spurring fresh safety concerns.

ALSO READ: Calls grow for reliable global Fukushima water monitoring

Akira Ono, Tepco's chief decommissioning officer, told the same briefing on Tuesday that its Kashiwazaki-Kariwa nuclear power plant, the world's biggest, did not observe "any specific damage" during the Jan 1 earthquake, which also affected the Niigata prefecture where the plant is located.

Japan's Nuclear Regulation Authority lifted an operational ban on the Kashiwazaki-Kariwa nuclear plant just days before the recent earthquake, but its restart time is unknown.